Project

Al Lusaily Reservoir, Dubai, United Arab Emirates

Efficient Special Designs

Dubai Electricity and Water Authority has completed building the water reservoir at Al Lusaily. The reservoir has a capacity of 450 million litres of desalinated water to improve and extend the city’s fresh water supply.

For MEVA KHK, it proved yet another succesful large-scale water project. The engineering team provided Ghantoot Contracting with design and formwork inventory for the columns, tank and baffle walls. Very fast pours to heights above 5 m were achieved with the heavy-duty formwork system Mammut 350 and its 100 kN/m² load capacity.

Columns with special design

The next challenge was pouring hundreds of columns with large mushroom- shaped column heads. MEVA engineers developed, designed and produced special L-shape steels units in two heights to handle all the pours easily and fast. The solution proved cost-effective and contributed to a zero hitch workflow.